Weeknotes for 2-6 May

This is the weeknote for the Open Revs & Bens project that covers the week 2-6 May.

What we did:

  • We were able to migrate the minimum data set necessary from Leeds’s Capita system into the Sedgemoor system
  • Shared with the project stakeholders the second draft of the open source governance document that we are working on.
  • User research had two business interviews and one internal one around business rates

What we learned:

  • We found that during migration some dates were not migrated due to its format so we had to change it to Year-Month-Day.
  • There’re some database constraints in the Sedgemoor system that need to be considered during the migration.